When it comes to off mains sewage many people can be blown away by all the information and differing products available on the internet, Google “domestic sewage treatment plant” and the consumer is bombarded by plants of all shapes and sizes .
T his is why dealing with a specialist manufacturer,
installer and servicer of treatment plants like We Build It Ltd can give the consumer piece of mind and con dence they are getting the right information, the right solution and the right system.
We Build It Ltd are based in the heart of some of Shropshire’s most outstanding countryside. As one of the UK’s largest manufacturers of domestic sewage treatment plants, we focus on high quality, a ordable products. All of our sewage treatment plants are based on the successful and simple extended aeration method. We can design, manufacture, install and service sewage treatment plant for single houses, small developments, rural industrial units, campsites, pubs, hotels, o ces, barn conversions and commercial applications. Our products can also be used after an existing septic tank to enable the e uent to be discharged directly to a water causeway, if your existing soak away has failed.
We often get asked;
- How does it work? What does it cost?
- Does it use electric?
- And how much?
- Do I have to maintain it?
- How do I install it?
- How big is it?
- Do I need to empty it?
- What can go into the plant?
- What happens to the waste?
- Do I need planning permission?
- Do I need to inform the
- Environment agency?
- How long will it last?
- DOES IT SMELL!!!!!?????
All of these questions can be answered by We Build It experts who know their products inside out; ask a middle man with no knowledge of the industry, product or process these questions and the customer is often baffled by terms such as BOD, COD, NH4, but do they really need to know this? All the homeowner, builder or architect wants to know is that the product will work with the minimum effort from them during the life of the plant.
We Build It Ltd offer straight forward, easy to follow advice for your sewage treatment needs.
All of our sewage treatment plants come with easy to follow installation and service manuals, as well as free telephone assistance by specialist installers. We can also o er full or assisted installations at very competitive rates. We pride ourselves on offering the best GRP products on the market backed up by proper good old- fashioned customer service – (dial straight through and speak to our specialists, no automated service or queuing system) buying a sewage treatment plant can be quite daunting, which plant is best for my situation?? What are the regulations?? What about the Environment agency?? Etc. but be assured we will be with you every step of the way, making sure you have the right solution designed around your requirements. You deal direct with the manufacturer, with over 25 years waste water experience, 24-7-365 days of the year.
For the self-builder the right treatment plant is simple to install providing they have taken the manufacturers advice, be aware some plants need complete concrete back ll which can add to install costs, a well-constructed plant such as the BioPure can be back lled with pea gravel.
Consider whole life costs, not just the cost of the treatment plant, factor in install costs, power consumption, servicing, consumable spare parts, product life cycle (guarantee) and emptying charges, We Build It Ltd o er a 25 year guarantee on the treatment plant and 2 Years on the air pump.
We can design, manufacture, install and service sewage treatment plant for single houses, small developments, rural industrial units, campsites, pubs, hotels, offices, barn conversions and commercial applications.
Simple solution sewage system
Any plant up to 50 people (pe 50) should be manufactured and tested to EN12566-3, this gives the consumer con dence they are getting the right treatment plant for their application, but always ask to see the certi cate and test results as these can be manipulated and not show the true outcome of the test.
Sizing the plant for a single house is simple its number of bedrooms plus two, so a three bedroom house is a 5 person treatment plant, for multiple dwellings using the same treatment plant speak to the manufacturer for the correct size unit, most manufactures range are in increments 1-5, 1-7, 5-13 etc. up to 50 person.
Model |
Bio-Pure 1 |
Bio-Pure 2 |
Bio-Pure 3 |
Bio-Pure 4 |
Bio-Pure 5 |
Bio-Pure 6 |
Bio-Pure 7 |
Bio-Pure 8 |
Bio-Pure 9 |
Bio-Pure 10 |
TWIN |
TWIN |
TWIN |
||||||||
No. of persons |
1 to 5 |
1 to 7 |
5 to 13 |
10 to 16 |
14 to 22 |
20 to 27 |
25 to 32 |
30 to 36 |
35 to 42 |
40 to 55 |
Max. average daily ow |
750 ltr |
1050 ltr |
1800 ltr |
2400 ltr |
3300 ltr |
4050 ltr |
4800 ltr |
5400 ltr |
6000 ltr |
8250 ltr |
Max. BOD/day |
300 g |
420 g |
780 g |
960 g |
1320 g |
1620 g |
1820 g |
2160 g |
2520 g |
3300 g |
In ground depth |
2.25 m |
2.25 m |
2.44 m |
2.74 m |
2.74 m |
2.98 m |
2.98 m |
2 x 2.74 m |
2 x 2.74 m |
2 x 2.98 |
Outside Diameter |
1.85 m |
1.85 m |
2.10 m |
2.10 m |
2.10 m |
2.55 m |
2.55m |
2 x 2.10 m |
2 x 2.10 m |
2 x 2.53 |
Inlet invert |
570 mm |
570 mm |
700 mm |
700 mm |
700 mm |
820 mm |
820 mm |
700 mm |
700 mm |
820 mm |
Outlet invert |
670 mm |
670 mm |
800 mm |
800 mm |
800 mm |
920 mm |
920 mm |
900 mm |
900 mm |
1020 mm |
Weight empty |
125 kgs |
125 kgs |
200 kgs |
230 kgs |
230 kgs |
350 kgs |
350 kgs |
460 kgs |
460 kgs |
800 kgs |
Total Capacity |
2270 ltr |
2270 ltr |
3000 ltr |
3975 ltr |
3975 ltr |
5610 ltr |
6000 ltr |
7950 ltr |
7950 ltr |
11220 ltr |
E Range |
27 w |
42 w |
65 w |
84 w |
130 w |
130 w |
210 w |
230 w |
280 w |
280 w |
The treatment plant you choose should be around 95% e cient thus allowing long intervals before de-sludge is required. The waste water must be cleaned to a standard meeting the usual discharge level requirement, you must apply for either an exemption certificate or permit, before making a discharge we can assist with this and advise on the method of discharge, be it a ditch, stream, watercourse or soakaway.
As the system breaks down and aerates the solids, the introduction of non-degradable items such as wipes, sanitary products etc. should be avoided at all times in any treatment plant, this will clog up the system and increase the need to empty the unit, follow this instruction and typical emptying will be around 3-5 years, it is also recommended no medicines, or harsh chemicals enter the unit, try to stick to Eco brands and stagger washing throughout the week.
Simple solution sewage system
We Build it has developed its range of package sewage treatment plants utilising proven SAF (submerged aerated filter) technology for maximum performance and reliability, using the most reliable energy efficient aeration blowers with a prolonged integral FlowPath system to maximise e uent quality.
All our Flowpath treatment plants are designed in accordance with the British Water Code of Practice for ows and loads, this range can be designed to meet your population and consent requirements, our standard range can accommodate up to 300 pe. This range of products can be designed for larger scale commercial applications such as camping sites, leisure facilities, schools, hotels, offices and industrial applications.
Maintanance, Spares And Servicing
The consumer needs easy to follow advice for their sewage treatment needs especially when servicing their plant, maintaining any sewage treatment plant, is a very important part of ensuring the efficiency of the system and that you adhere to any operating and maintenance manual and annual servicing.
We strongly advise servicing the system on an annual basis and this will take on average less than an hour to complete. It will also help you to meet your legal requirements with the Environment Agency.
We Build It Ltd Service Contracts
- Emergency breakdown cover for 12 months. If you have any problem with your unit, call us and we will come out and x it free of charge.
- One service visit where all necessary checks are carried out. This includes assessing the aeration pattern, sludge levels and e uent quality.
- All labour expenses for servicing and call outs are covered so there are no hidden costs.
- The cost of all serviceable parts will be free of charge. This includes rebuilding the air pump, replacing the diaphragms and also the air lters.
- Sludge return is carried out as required. This is the removal of settled sludge from the outer scum ring back into the centre chamber to be re digested and treated again. This helps to keep the emptying period low.
- Emptying is NOT included in the agreement as the Bio-Pure does not require emptying for 3-5 years.
- The service agreement lasts for 12 months and will also help you meet your Environment Agency obligations regarding your Consent to Discharge. This includes keeping records of service, de-sludging and maintenance work for a minimum of 5 years.
Our Other Products include Mini SAF’s (for o ces and outbuildings up to 4 persons) Pump Stations (standard and bespoke)
Septic Tank Conversion Units (used as secondary treatment for underperforming septic tanks)
For a full range of our products and servicing visit www.bio-pure.com www.webuildit-ltd.co.uk